Click4Assistance UK Live Chat Software
Skip to main content

Chester City Walls

Current work on the Walls

Collapse on the City Walls by the Eastgate Clock

Background

In 2020 a section of Chester’s City Walls collapsed close to the famous Eastgate Clock.

Enabling works, including vegetation removal were completed this summer in preparation for the main repair works.

Latest update

Preparation work has started and passers-by may have noticed the preparation of the concrete footings for the scaffold ramp that will be built to access the site under the Grosvenor Shopping Centre car park access ramp. 

Further updates will appear on this page.

Repair programme

Originally the curtain wall of a Roman fortress, the City Walls have undergone many programmes of repair or rebuilding through the centuries, often with no or minimal records of what took place. So, the City Walls today form a complex and not fully understood series of constructions, including Roman, Medieval and Victorian.

The construction at this location has not been previously investigated making this an incredibly complex repair project, which also requires Scheduled Monument consent.

Scaffold propping has been designed to support the partially-collapsed inner wall to prevent any further damage, with a roof added for further protection. This will be installed in the first phase of the repairs.

Schedule

Site set up

What When
Dee House Completed October 2024
Grosvenor car park October and November 2024
Baseline surveys (noise, air quality and vibrations) October and November 2024

Stage one - Temporary Works

What When
Access ramps at Grosvenor car park site November 2024 to January 2025
Access ramps at collapse site January to February 2025
Groundworks, construction of support frame foundation and erection of main support frame February to May 2025
Roof structure and propping to sides of collapse site May to July 2025
Further supports to collapse July to Aug 2025

Scheduled Monment Consent for Stage two

What When
Package issued to Historic England March 2025
Stage 2 consent obtained July 2025

Stage two (only indicative)

What When
Works begin July 2025

Works complete

  • Site investigation works completion - January 2026
  • Scheduled monument consent obtained - July 2026
July 2026

Stage three

What When
Works begin TBC
Works complete TBC

Further details

Previous works

Following the collapse, to ensure that residents, visitors and businesses could continue to enjoy this section of the City Walls our engineers, alongside external specialists, designed a temporary walkway which is incorporated into the scaffolding needed to prop up the wall.

The scaffold was carefully designed to protect the Wesley Church Centre, take into account crypts and other buried archaeology between the Church and the City Walls, and maintain a fire escape route for the surrounding buildings.