Temporary road closures
What you will need before applying
Before making an application please note the following conditions and requirements:
- you will need to check whether your proposal will clash with any other temporary road closures, more information can be found on the Roadworks.Org website
- if the closure is agreed it is the applicant’s responsibility to identify and notify all residents and businesses directly affected. This notification should be at least ten days prior to the works commencing, unless other arrangements are agreed as reasonable by the overseeing authority.
- if the planned duration of the road closure is more than five days, the application must be submitted eight weeks before the planned start date, to allow for statutory advertising in local newspapers
- if the planned duration of the road closure is less than five days, the application must be submitted a minimum of four weeks before the planned start date
- in the case of emergency road closures that are required immediately, the application can be made retrospectively as soon as reasonably practicable
- the applicant or their traffic management contractor will be responsible for signing the diversion route and / or any temporary restrictions, and will be responsible for maintaining all necessary signs
- for planned works, advance warning signs are required to be placed at each end of the restriction. Warning signs should be in place 14 days prior to the works commencing, unless other arrangements are agreed as reasonable by the overseeing authority.
- all traffic management must comply with the Safety at Street Works and Road Works Code of Practice issued by the Department for Transport
- ensure that all signs are maintained and removed upon completion of the restriction
- applications from utilities and traffic management companies must include a Streetworks Permit or Section 50 licence reference number
We will also need a 1:1250 or 1:500 scale plan of the proposed site clearly showing the:
- accurate location and length of restriction including road names
- accurate location and length of diversion route including road names, designed by a competent traffic management company
- signing schedule showing details and positions of temporary traffic signs for the diversion
- proposed access arrangements for pedestrians and cyclists - if access cannot be maintained, reasons must be given